Civil Blogs

River Bank and River Training works

2024-05-08 12:25:54
Share On Social Media :
River Bank and River Training works
River training works are constructed for a variety of reasons, but the fundamental objective is to restrict horizontal movement of river channel by guiding and training the flow. 
Objective of river training works
1.      To train the river to flow in straight reach both U/S and D/S well as at the bridge site.
2.      To deflect the flow of the river from the banks to prevent the erosion of the bank.
3.      To provide the guide bund so as to confine the stream in the desired limits.
4.      To provide the required depth at the bridge in case of navigational channels.
5.      To confine the span to minimum.
River Bank may be failed by
1.      Erosion of soil by river currents or waves
2.      Excessive hydrostatics pressure in the material in the bank or sloughing of slop due to saturation of bank materials
3.      Under mining the toe of bank due to high current, eddies etc.
4.      Liquefaction and subsequent movement of soil mass by piping
5.      Formation of sink hole due to water in the dispersive soil.
Type of river training works
1.      Embankments
2.      Guide banks or bund
3.      Groynes or spurs
4.      Pitching of banks and sub siding
5.      Revetment work
6.      Pitched islands
7.      Cut-offs
8.      Closing dykes
 Techniques for Bank protection/Stabilization
Two broad ways such as the direct methods of protecting the slope and the indirect way by providing structure that extend into the stream channels and redirect the flow so that hydraulic forces at the channel’s boundary are reduced to a non-erosive level.  Among the direct method some of are
1.      Self-adjusting armour made for stone or other materials.
2.      Trench fill revetment/windrow revetment/longitudinal stone toe
3.      Slope pitching
4.      Lining with cement concrete
5.      Spur/stud
6.      Riprap
7.      Launching apron
8.      Flexible mattress etc. 
Embankment
Embankment on either approach banks are provided to protect the adjoining area getting submergence. 
Guide Banks
The main purpose of these banks is to divert the stream from comparatively larger area to the confined section under the bridge. These bunds are constructed in pairs on either banks and provide a streamline flow at the bridge site. It is made of earth and sometimes inner face is covered with stone or concrete block. The U/s length of bund is in between 1L to 1.1L times the length of the bridge while down stream length is usually kept 0.2 times the length of the bridge.
                    The radius of U/S side decide depth of scour as well as velocity of flow while D/S side is half of the U/S side. A free board of 1.2 to 1.5 m is provided above the HFL. An apron equal to 1.5 D should be provided at the toe of guide banks. 
Pitching of banks and subsiding apron
The banks are very often protected by stone pitching, bushes, wood, plants, concrete blocks or grass. The slope of such pitching depends up on the material used for pitching. Proper care should be taken that toe is properly protected otherwise the pitching would be damaged/destroyed during flood.
     The launching or subsiding apron of loose stone is therefore provided at the top of the river bank up to the required length in the river bed. For launching apron, if the average velocity up to 3.5 m/s, stone having weight 40 to 70 kg can be used and if the velocity is more than 3.5 m/s concrete block is useful. 
Revetments
Failure of a revetment is often result of inadequate protection against scour at the toe of the revetment. There are various types of material used for revetment such as gabion filled with stones, sand bags, stone riprap, timber piles, bamboo piles, old tires, concrete slabs, concrete blocks and also combination of two or more of these materials.
Pitched islands
Pitched island is artificial island constructed in the river bed when it is required to prevent the flow of river getting confined to one bank only. The stone pitching used to form the island obstructs the flow of water which becomes turbulent. This results in the scouring of the bed. As the bed gets lower, the water from the other bank gets diverted to this bank and the flow along the far bank is reduced. Pitched island is protected by stone pitching.
Cut-offs (to control the meandering of the river)
                          Sometimes the river develops horse shoe hair pin ben during floods the area between the horse shoe gets submerged and the river starts flooding along the straight line. Due to the reduction in the length of the channels the slope becomes steeper and the portion U/S of the cut off undergoes erosion. As a result of this the D/S gets silted up and disturbance are caused in the river. If, however the straight portion is dug up, the river water will start along this straight portion and curved portion would be get silted up.
The chances of the river changing the courses are practically eliminated.
 
Closing Dykes
Sometimes the river flows in the main as well as in a subsidiary channel and the river has a tendency to change its course towards the subsidiary channel. This tendency of the river is checked by providing a closing dyke. It may be solid, permeable natural soil like brush wood, branches of trees et
The solid material stops the flow into subsiding channel while permeable materials reduce the velocity of water. As a result of this, the subsidiary channel gets silted up in course of time and the flow of river gets confined to the main channel.
Groynes/Spur/Stud
Groynes deflect or guide flow away from the vulnerable river bank. They can therefore be used both for bank protection and help maintain a navigational channel. It is made of timber, masonry, concrete or earth etc. Based on the orientation, it may be repelling, deflection or attracting spurs. Porcupine (tetrapod) is permeable spur which helps for siltation along the banks and made of bamboo, timber, gabion etc.
Point to be considered for Spur
1.      Height of spur must be more or equal to maximum flood level
2.      Launching must be provided sufficiently
3.      Retard must be permeable.
4.      The length of retard line should correspond to the amount of an eroded river bank that, it is to be recovered by deposition.
5.      For velocity reduction along an eroding bank, retard should be placed in lines perpendiculars to the bank with line spacing about.
Design Consideration.
Spur length, L: generally, 1/3th of river width but not more than 200m
Spur Spacing: 3 to 4 L or LcotA, A is an angle deviation of spur orientation
Top width 3 to 6 m at formation level
Free board 1 to 1.5m above HFL or 1 in 500 yr return period flood
Side slope 2:1 to 1.5:1
Thickness of pitching for spurs (t) 0.06 Q1/3 , Q in Cum/sec.
 

Leave a Comment